SONGS is looking for information on dose estimates in P6:

We have been struggling with maintaining daily dose estimates specifically during our current dual unit outage. We are working from large spreadsheets and adjusting the numbers daily when work moves or slips in the schedule. Unfortunately this can occur frequently while 2 units are down and competing for resources from the same pool. This is a very cumbersome and difficult process to maintain and are looking to develop a more automated process using our current software.
We have an in-house developed oracle based software program for REP processing and dose tracking, SAP for maintenance orders and P6 for scheduling. We have some ideas but are looking to see if and how other sites are handling this.

Does your site input dose estimates in P6?
If yes please send me an example of the format.

Does this occur automatically or is it input manually in P6?

Do you include only maintenance dose estimates in P6?
If you include dose for other divisions that do not work from work orders such as Operations or Health Physics, are they input manually in P6?

Thank you,

Roger Scott Sherman
Technical Specialist Scientist
ALARA Planning Department
San Onofre Nuclear Generating Station
P.O. Box 128, San Clemente, CA 92672
949-368-6423

[email protected] ----------------------------------- Powernet - a service of the Health Physics Society Power Reactor Section Powernet archives at http://www.mail-archive.com/[email protected]/ Reply to: [email protected] If Questions, contact Mike Russell, CHP at [email protected]