Duke Energy RP milestones:

Number: M-6b
Description: Preliminary Dose Estimate
Window: T-15 to T-12
Owner: Radiation Protection Manager
Expectations and Deliverables: RPM - Develop an outage dose estimate and 
compare against the current fleet and industry goals, identify known 
vulnerabilities, and present the results to the ORB. RPM - Ensure that the 
known vulnerabilities and variances are being monitored and are being tracked.
Milestone Requirements: Milestone met if the milestone owner and Outage Manager 
agree that the expectations and deliverables were met with integrity prior to 
T-12:
Required Performance Indicator(s):
Not required
Logic: The T-15 start milestone allows Radiation Protection Manager to start 
developing the dose comparison as soon as ENG completes their validation and 
review of the Outage Scope Plan and after WCG has developed a shell schedule 
that can provide a projected outage duration. The T-12 milestone closure allows 
dose considerations to be factored into the scope certification process and 
also the development of the outage scope plan.
Comments: The T-15 to T-12 window does not coincide with the annual goal 
setting cycle for Fall outages. The Fall estimate will be estimated mostly from 
typical routine work, the targeted outage duration, and any information already 
in the Long Range Plan.


Number: M-25
Description: RWP's and TSR's Identified and Completed
Window: T-5 to T-1
Owner: RP Manager
Expectations and Deliverables: RP - At T-5 begin identifying RWP's needed to 
support outage scope RP - At T-1 RWP's are completed and ready for use RP - By 
T-2 ensure all TSR's have been delivered to Engineering for approval ENG - At 
T-1 ensure all TSR's have been approved and ready for use
Milestone Requirements: Milestone met if the milestone owner and the Outage 
Manager agree that the expectations and deliverables have all been met with 
integrity.
Required Performance Indicator(s):
Not required
Logic: The T-5 milestone start coincides with the issuance of the Initial Logic 
Schedule - Rev B Schedule. The T-1 milestone closure ensures one month for 
crews to complete walkdowns and prep efforts.
Comments:



-----Original Message-----
From: [email protected] [mailto:[email protected]] On Behalf Of 
[email protected]
Sent: Tuesday, March 05, 2013 3:23 PM
To: [email protected]
Subject: Powernet: RP Outage Planning Milestones


Requesting copies of your refueling outage planning milestones related to 
Radiation Protection.  Thank you in advance.


-----------------------------------------
The information contained in this message is intended only for the personal and 
confidential use of the recipient(s) named above. If the reader of this message 
is not the intended recipient or an agent responsible for delivering it to the 
intended recipient, you are hereby notified that you have received this 
document in error and that any review, dissemination, distribution, or copying 
of this message is strictly prohibited. If you have received this communication 
in error, please notify us immediately, and delete the original message.
-----------------------------------
Powernet - a service of the Health Physics Society Power Reactor Section

Powernet archives at http://www.mail-
archive.com/[email protected]/

Reply to: [email protected]
If Questions, contact Mike Russell, CHP at [email protected]
-----------------------------------
Powernet - a service of the Health Physics Society Power
Reactor Section

Powernet archives at http://www.mail-
archive.com/[email protected]/

Reply to: [email protected]
If Questions, contact Mike Russell, CHP at
[email protected]

Reply via email to