Hi All,
Do you have a formalized process for suspending Emergency Responder
qualifications due to RP issues. For example:
1) Do you allow declared pregnant workers (DPW) to fill control room minimum
staff shift positions? If not, do you have a formalized process for suspending
a qualification or is the process tracking manually.
2) Do you allow DPWs to fill RP/Chemistry Technician minimum staffing shift
positions? Again, if not, do you have a formalized process.
Diablo Canyon does not allow DPWs to fill a control room min staff position
because the postulated worst case dose calculation for control room personnel
is above 500 mrem. Similarly, a DPW RP/Chem technician cannot fill one of the
minimum staffing positions on backshifts or weekends because they are not
eligible for emergency exposures. We do not have a formalized process of
actually suspending qualifications but we have been asked by our Operations
organization to evaluate available options.
Thanks in advance,
Linda
Linda M. Sewell, CHP
Principal Health Physicist
Pacific Gas & Electric Company
Diablo Canyon Power Plant
MS 119/1/117
PO Box 56
Avila Beach, CA 93424
P: 805.545.4315 | F: 805.545.2618| [email protected]<mailto:[email protected]>
PG&E is committed to protecting our customers' privacy.
To learn more, please visit http://www.pge.com/about/company/privacy/customer/