I didn’t receive any response to this November 20th powernet so I am trying it 
again.


What environmental LLD Δt  do other facilities use for their REMP samples?


1)      elapsed time between environmental collection, or end of the sample 
collection period, and time of counting

OR

2)      the midpoint of the sample collection period and time of counting
-----------
During a Review of our REMP program the following was identified:

NUREGs 1301 and 1302 define the environmental LLD Δt as the elapsed time 
between environmental collection, or end of the sample collection period, and 
time of counting (see NUREG 1301/1302, Table 4.12-1, notation (3)). This is 
different from the Δt definition used for liquid and gaseous effluent LLDs, 
which is defined relative to the midpoint of the sample collection period. See 
NUREG 1301/1302 Table 4.11-1, notation (1) and Table 4.11-2, notation (1).

Michael Macho
Radiaiton Protection
Comanche Peak Nuclear Power Plant
6322 North FM 56, Mail Code 005A
Glen Rose, TX  76043
254-897-5698 (Office)
817-559-1997 (Cell)

[cid:image002.png@01D1B9B2.48A19000]
[Excellence_SQSgreen]