Qs. A project was budgeted at $1,000,000. The project is meanwhile being 
executed, and the following current figures have been assessed: PV: $500,000 
EV: $450,000 AC: $550,000 Assuming that the Cost variance was caused by 
one-time cost drivers, which are no more effective, what Estimate at completion 
(EaC) can you derive from these figures?
A. $900,000
B. $1,000,000
C. $1,100,000
D. $1,222,222

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC4011

This question is sponsored by
Over 1800+ PMP Simulated Questions
http://bit.ly/pmsimulator


Good luck for PMP Exam.

Regards,
PM Guru
[email protected]

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to