Qs. A project underwent a major Scope change, which increased cost and work 
levels. What does this mean for Earned value data?
A. The cost baseline will be updated and the new baseline will be the basis for 
future earned value analysis.
B. As baselines should generally not be adjusted, the project is due to exceed 
its budget from now on.
C. There are several reasons to change a baseline, but not scope changes. The 
project will exceed its budget.
D. Earned value analysis becomes useless after a scope change, the technique 
should not be used any more.

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC4009

This question is sponsored by
Outwitting The PMP Exam
http://clk.im/outwitpmp


Good luck for PMP Exam.

Regards,
PM Guru
[email protected]

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to