Hi All,

The following PMP® exam sample question is taken from the Free PMP Exam
Simulator:

------------------------------

You just took over the management of an industrial construction project,
which is in the execution phase. You determine that your team is
communicating directly with their client company's peers. According to the
Communications Management Plan, all client interaction should be performed
through the project manager. What is the potential reason for your team's
behavior?

A) The Communications Management Plan is not comprehensive.
B) The Project Management Plan has not been shared with the team.
C) The previous project manager is not a PMP.
D) The Communications Management Plan was later updated.

------------------------------
Hint: The Project Management Plan contains the Communications Management
Plan.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by
at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free
for 3 days. We also offer 110 free questions at
http://www.free-pm-exam-questions.com. We are a PMI Registered Education
Provider.

Please click here
<https://www.facebook.com/questions/10150308450269970/>for the correct
answer and explanation.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC -
http://www.project-management-prepcast.com

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at http://groups.google.com/group/project-managment.
For more options, visit https://groups.google.com/groups/opt_out.


Reply via email to