Thanks Jason. I'll move the appropriate stories over to 31 in Agilo.
-Todd On 11/29/2011 12:41 PM, Jason L Connor wrote:
Due to working on other bugs including the learning curve of maintaining a 3rd party module, I won't complete the work on the Coordinator this sprint. Here's a break down of the stories and the progress I've made/will make on them this sprint. #8184 Coordinator: Design completed #8186 Coordinator: Scheduling on track to complete most of this story with the exception of #8190: tie into coordinator #8192 Coordinator: Tasks and Tasking only peripheral work on this story will get to #8194: augment task search with tagging but nothing else # 8199 Coordinator: Coordinator Package will not get to this story at all _______________________________________________ Pulp-list mailing list [email protected] https://www.redhat.com/mailman/listinfo/pulp-list
_______________________________________________ Pulp-list mailing list [email protected] https://www.redhat.com/mailman/listinfo/pulp-list