> Rony a écrit :
>> It looks like I forgot to specify that the product is a totaly new
>> product build from scratch, not an upgrade from an existing product.
> 
> 
> Still the advice to first find out what went wrong with the previous
> project is a very sensible one. Technical problems do exist, but from
> experience they rarely are the main source of failure.
>
And be sure to look into the estimation and costing methods the company 
is using. IOW are you sure whether design/build/test phases are 
overrunning a sensible estimate or if the initial costing and estimation 
is underestimating the project size?


-- 