On 7 June 2016 at 20:15, Michael Roth <mdr...@linux.vnet.ibm.com> wrote:
> Quoting Peter Maydell (2016-06-07 13:45:06)
>> But I think the real problem with a schedule which expects a
>> release at the tail end of August is that we then only have
>> three and a half months left til mid-December which is in
>> practice the latest we want to do a release given holidays.
>> So we can only avoid the short dev period this time round by
>> having a short one next time instead.
>>
>> Maybe we could have +1 week rather than +0 or +2 (so softfreeze
>> 28 June, rc0 19 July, release 16 August), as you suggest. That's
>> currently feeling like the best compromise to me.
>
> Yah, I think I agree. We'll have to make up the 2 weeks lost at some
> point, but spreading it out avoids us finding ourselves in a similar
> situation next release. Seems like maybe there may be more work
> being targetted for 2.8 as well.

OK. I have updated 2.7 with the +1week dates (and removed the
note about them being tentative), so let's go with that.

thanks
-- PMM