Andrew:
It is not in the code. It is an argument you make to your own AHJ.
William
At 10:57 AM 1/12/2010, you wrote:
Team wrenches - I feel like I've seen a provision in the Code for
installing a sub-panel to aggregate PV inverter outputs for the purpose of
simplifying the actual grid connection (such as for a line-side tap) but I
can't find it in 690. I also seem to remember specific verbiage that
needs to be on the panel along the lines of "PV circuits only. Do not add
load breakers." to ensure compliance with 690.64(B). Does anyone know
where I can find this info in the NEC?
Andrew Truitt
Standard Solar Inc.
_______________________________________________
List sponsored by Home Power magazine
List Address: RE-wrenches@lists.re-wrenches.org
Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org
List rules & etiquette:
www.re-wrenches.org/etiquette.htm
Check out participant bios:
www.members.re-wrenches.org