Hello Joel --

Well, you can be assured that both NREL and IREC are on your side. They were very convincing about dropping UEDS requirements at this seminar. Funny how utilities can require UEDSs, but none of them have the procedures, personnel or infrastructure to actually *use* them.

Imagine a 'green neighborhood' with PV on each of four dozen homes. Figure at least 10 minutes each for the utility to locate and tag / lock out each UEDS...and the same to re-commission them after the incident. And how many utility trucks carry 4 dozen locks?

I won't go into any more UEDS issues here, but I will be writing about them soon and publish the link here on the list.

DAN FINK



Joel Davidson wrote:
Hello Dan,

Many of us have worked hard to eliminate the UEDS requirement. Unfortunately, each utility and building & planning jurisdiction will have to be convinced by local contractors. Some will have to be re-convinced when the next authority gets into power. Please, someone tell me that I am wrong.

Joel Davidson
_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to