Wrenches,I have an off-grid client who is going to be connecting to the grid.  
Since the system (~9 kW of PV and ~2400 Ah battery) is already well suited for 
the loads, I am wondering about the necessity of an essential loads panelboard. 
 I'm not sure if I see the need since the battery is already sized for all the 
existing loads.
The intent is to continue running all the loads from the battery and have the 
(Outback) settings so that the grid is only used when the PV isn't able to 
maintain a particular battery voltage setting.  
Comments, insights into this type of set-up?
Thanks,benn
DayStar Renewable Energy Inc. www.daystarsolar.ca780-906-7807 Certified 
Construction Electrician Solar Photovoltaic Systems CertifiedCertificate # 
0007SHAVE A SUNNY DAY                                          
_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to