UL evaluates products on internal temperature rises while it is used
normally.
They also evaluate the products under abnormal use, in various ways.
It may or may not have a fan. If you look inside an inverter, you will
see the same type of
things.... Large external battery cables connecting to smaller internal
cables and/or
bus-bars and circuit board traces. All sorts of things that probably
are not allowed
with NEC.
I think I saw a temperature of 150 degrees F mentioned here. That's nothing
compared to the highest temperatures seen in certain parts of the products.
Some wire, like in some transformer classes can reach as high as 220
degrees C (428 F) !
boB
On 5/25/2016 11:39 AM, Kevin Pegg wrote:
Hi Daniel,
Appreciate your thoughts on this.
- This wire is contained inside 2" flexible metallic conduit, approx.
3' long from the alternator to the external breaker. Some of it is in
free air, but most is contained within the conduit.
- the main breaker is a 100% rated 175A.
- This is an industrial generator is rated for continual operation at
full load, and my expectations is all the wiring in that unit is
suited to that. Will the site actually draw that? It is entirely
possible during heavy loads & concurrent battery charging that it
could well be running at max load for hrs at a time.
The plastic bushing is easy to remedy, as is the ground lug.
The wire is where I am not sure what to do. Everything I am hearing
tells me that the #4 wire is undersized. So there is a dilemma. If I
replace the wires myself then I believe I have voided the UL
certification. But think have made a safer engine for my client. At
the end of the day, it will be me who the client is calling if there
is an issue.
Just for kicks I opened up a couple 25 kW gens and factory wiring was
either # 2 or # 4 for this same purpose. Hmm.
Kevin
*From:*RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org]
*On Behalf Of *Daniel Young
*Sent:* May-25-16 7:24 AM
*To:* 'RE-wrenches' <re-wrenches@lists.re-wrenches.org>
*Subject:* Re: [RE-wrenches] Generator factory wiring issues
Kevin,
Based on what the engineer said, I think you both make valid points.
On the 4AWG wire:
Type Z wire (150 C insulation) is rated for 190A based on 2014NEC
table 310.15(B)(19). It’s rated for 120A when in conduit. So is this
wire where you might call it in conduit or free air? I imagine the
inside of a generator enclosure is somewhere in the middle. Also I
assume this is Z type or similar based on the response stating 150 F
(I know he meant C) wiring is used.
Is this on a 175A breaker? If so then it should only pull 140A
continuous (maybe it’s a 100% rated breaker?). And that really would
not be great for a generator. Usually we only design for a maximum of
80% loading on a generator depending on elevation and a few other
de-rate factors. In reality do you expect more than 120A to be a true
“continuous” load on this unit. I don’t know the answer, just worth
thinking about.
Plastic bushings:
I sure would want them in a vibrating machine like a generator, but if
UL does not force them to, don’t expect them to include it.
(Capitalism at work). You might be able to use an electricians trick
where you cut a PVC bushing and slip it over the existing wire, then
you can thread it in the end of the fitting and it is 95% as good as a
normally installed bushing…. I would not do it on a new install, but
it’s a useful trick when you walk up on existing mistakes.
Lug:
You could continuity test it to see if it’s a good connection,
otherwise that strikes me as no good either. Just another cost saving
step for the manu at the clients expense in my opinion. It’ll work
fine for now, but not likely in 5-10yrs as corrosion sets in. I’d just
throw a star washer underneath if possible, but it sounds like the
stud is not long enough.
So there is a little bitta’ code and a lotta’ opinion.
With Regards,
Daniel Young,
NABCEP Certified PV Installation Professional^TM : Cert #031508-90
*From:*RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org]
*On Behalf Of *Kevin Pegg
*Sent:* Tuesday, May 24, 2016 6:14 PM
*To:* RE-wrenches <re-wrenches@lists.re-wrenches.org
<mailto:re-wrenches@lists.re-wrenches.org>>
*Subject:* [RE-wrenches] Generator factory wiring issues
Wrenches,
Recently, we took delivery of a 40 kW LPG generator made by Gillette.
Inspecting the factory wiring of the unit, I had some concerns which
are outlined in detail below, with an engineer's response inline. The
concerns are using #4 wire to pull 175A; no plastic bushings on
metallic conduit, and ground lugs on top of painted surfaces / and
insufficiently torqued.
The engineer response has left me somewhat baffled / frustrated in
that I do not feel that actual issues have been addressed. I don't
really care what UL or any other authority tells me - pulling 175A
continually for many hrs through a #4 wire I think is asking for
trouble. And my customer won't really care about what the UL ratings
say if they are dealing with a melted alternator.
Am I missing something here?
Kevin
RE: SP-410-1-1LO S/N:
I am responding to the concerns written below both in the capacity as
designer and as U.L. liaison.
We have received this generator, mostly intact. Some freight damage to
the battery support cross member due to forks not extending the full
depth of the crate, and are working with the freight company to
resolve that.
Sorry for the experienced freight damage.
However, there are some SERIOUS and DANGEROUS issues pertaining to the
wiring of the alternator! It is obvious that wiring was not done by an
electrician.
There are no serious or dangerous issues on this (built to U.L.
recognized spec) Gillette Generator as referred to in this writing.
And – you are correct- this wiring, as ‘factory wiring and not ‘field’
wiring, does not require or use the specific qualifications of a
licensed electrician. The well trained/supervised workers here at
Gillette have many years of experience building the product and are
guided as need by a competent engineering staff.
Specifically:
- Alternator to circuit breaker wiring was done with #4 wire (rated
60A max). Per your own load chart inside the breaker enclosure (photo
attached), that wire should be 4/0 to carry the 175A that this
generator is capable of producing.
This observation is incorrect. The load wiring sizing schedule affixed
to the side of the circuit breaker box is for ‘field connectivity’ at
75 deg. F. We do our ‘factory wiring ‘ on a different schedule using
load cabling from the generator to the top of the circuit breaker
rated at 150 deg. F. All of this cabling has been done, tested and
proven by U.L
- There were no plastic bushings (see photo) where the wires exit the
metal conduit.
The conduit bushing involved is the correct U.L. approved component
for the installation of spiral wound metal conduit required to be
installed on ‘open’ style generator assemblies. A plastic bushing is
NOT required as this is again ‘factory wiring’, not ‘field wiring.
- What would have happened here is the wire heats up due to gross
under sizing, melts the insulation, and shorts it out. Resulting in a
fire or destruction of the brand new alternator, and the associated
legal proceedings involving all parties and a general nightmare for
all of us.
disagree, on several fronts. Referencing the specification standard
U.L. 2200, many times- local inspectors blur the line between its
dominance for standby generator systems and NEC-70 (NEC- code). The
former covers ‘factory’ design wiring on stationary standby generators
subject to witness testing by a U.L. certified representative. The
latter applies to ‘field wiring’- that is anything outside the box
including connection conduits, load wiring ( at 75 deg. F) transfer
switches, distribution panes and the like. As resident designer for
the past twenty-six years, I have myself- written eight standards/code
rebuttals successfully, both for U.L. and local inspectors. Comparing
a 4ga, 2ga, 1ga and the like against a different class of wiring such
as a 4/0 would certainly be cause for alarm. But, clearly here_the
alarm is unwarranted_.
- the ground lug on the alternator was not fastened
properly (a short stud with a nut on it - no way to get proper torque
on it - should be a bolt), and both this lug and the lug inside the
breaker enclosure was fitted on top of a painted surface. Every
electrician knows you need to scrape off the paint so as to allow for
proper conductivity.
This lug is not supplied by us. It is supplied as part of the
generator construction built by Marathon. Marathon generators are
certified for U.L. 1004B- generator assemblies and U.L. 1446 for
insulation. This is the equipment issued as part of that U.L.
certified design. as to their design vs. a ‘bolt’ going into the
threads of the hole- if it was really an issue, it would not have
passed their U.L. certification testing. Their generator assemblies
bear their U.L. file certification under R/C (JZGZ2) and listing
(JZGZ). In regards to the paint removal, the engine and generator are
cable grounded to the frame of the generator assembly and serrated
hardware is used during assembly to scratch into the painted surfaces
of the boxes and frame. As you notice in the picture- the threads in
the generator housing sleeve- are not painted.
These are issues that we are able to remedy. But my
client, being very hands on has noticed this and inquired, quite
reasonably, as to why they are paying Energy Alternatives to repair
something that they paid for and should have been delivered properly
done in the first place?
To my findings, there is no warrantable work required.
I think the fairest solution to this is for us to
remedy these defects and to have Collicutt reimburse use for time and
materials. I will complete the work and send you the total bill for
compensation unless you would like to approach this in a different
method. We are hoping to go live with this unit in the next few days
once the gas fitting is completed.
As stated above- Not required.
I hope these responses help clarify the items in question.
Regards,
_______________________________________________
List sponsored by Redwood Alliance
List Address: RE-wrenches@lists.re-wrenches.org
Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
List-Archive:
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html
List rules & etiquette:
www.re-wrenches.org/etiquette.htm
Check out or update participant bios:
www.members.re-wrenches.org
_______________________________________________
List sponsored by Redwood Alliance
List Address: RE-wrenches@lists.re-wrenches.org
Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
List-Archive:
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html
List rules & etiquette:
www.re-wrenches.org/etiquette.htm
Check out or update participant bios:
www.members.re-wrenches.org