Jay,
 
You need to provide more information. The 2014 NEC is a significant improvement 
in the language related to single-phase inverters on a 3-phase service. To read 
it any other way shows a very large misunderstanding of the language.

It should be much better on the 2014 NEC, not worse. Where do they not get it. 
The old language was used routinely to prevent single-phase inverters on the 
3-phase systems. I wrote the change to the 2014 that greatly improves the 
language.

Bill.

-----Original Message-----
From: RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org] On Behalf 
Of jay
Sent: Tuesday, March 21, 2017 6:35 PM
To: RE-wrenches <re-wrenches@lists.re-wrenches.org>
Subject: [RE-wrenches] 2014 NEC 705-100 (A)

HI All,

I’ve got a client who’s having some issues with the building department. (for 
the 705-11-A  NEC 2014) Now it is true that we in California are now in 2014 
NEC) They are saying that he isn’t allowed to install the 3rd  inverter onto a 
3 phase service ( this system was done in stages, using SMA 3kw for phases 1 
and 2) Now they are being stopped on adding the 3rd.

Anyone ever run into this before?
Any answers?

thanks

jay


_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org


_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org

Reply via email to