Howdy all,

This is a formal request from the KDEPIM team to add a 2 week delay to the
4.6 release schedule and to use that extra 2 weeks to add another beta release.

We really need the extra time; data migration is still taking time to get right.

This would also delay the Git transition for KDEPIM and others the same 2 weeks.

The proposed change would look like this:

# 1.11 Monday, January 3, 2011: Tagging Freeze for Release Candidate 1 <<== Git 
Migration
# 1.12 Monday, January 3 2011: Hard API Freeze
# 1.13 Monday, January 3, 2011: Hard Message Freeze
# 1.14 Monday, January 3, 2011: Artwork and Bindings Freeze
# 1.15 Tuesday, January 4, 2011: Release Candidate 1 Tagging
# 1.16 Wednesday, January 5, 2011: Release Candidate 1 Release 
# 1.17 Monday, January 17, 2011: Tagging Freeze for Release Candidate 2
# 1.18 Tuesday, January 18, 2011: Release Candidate 2 Tagging
# 1.19 Wednesday, January 19, 2011: Release Candidate 2 Release
# 1.20 Wednesday, February 2, 2011: Final Tag
# 1.21 Wednesday, February 9, 2011: Release

Thoughts?