Hi.

I suspect that many Scalr customers have been asking for the option to 
specify which role(s) within a farm should be 'spun up' in parallel or 
sequentially.  If this is not a feature, I'd like to ask for an evaluation; 
i suspect that there's a fair bit of internal er-engineering that must 
occur for this feature to make it into Scalr.

Example:
I have a Farm with 32 roles.  The first 4 roles in this farm *must* come up 
sequentially.  After the first 4 are up, the remaining roles can come up in 
parallel.  Unfortunately, this is not something i can currently with one 
farm. 


SO.  Scalr currently can't do what I need.  This means that I must now 
start to break this entire farm into two farms so that I can cut down the 
'spin up' time for all the roles (4 sequential + 28 in parallel versus all 
32 in sequence).  Two separate farms is the problem that leads me to my 
question.

So, my question:

*Is there a way to have one farm 'trigger' the creation of another?*  E.G: 
farm01 has 2 "HostUp" events associated with it --> change farm02 from 
'terminated' to 'running'* on the Scalr server?*

I suspect that I will be able to do this with my own custom scripts, but 
I'd like to avoid that if possible.

Please let me know what my option(s) are as well as if my feature request 
has made it onto the Scalr roadmap at all.

Thanks!


-Karl

-- 
You received this message because you are subscribed to the Google Groups 
"scalr-discuss" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
For more options, visit https://groups.google.com/d/optout.

Reply via email to