Re: Scheduling 9.3
On Thu, 2017-11-16 at 08:02 +, Adam D. Barratt wrote: > On 2017-11-15 18:30, Steve McIntyre wrote: > > On Wed, Oct 25, 2017 at 05:00:16PM +0100, Adam Barratt wrote: > > > On 2017-09-24 17:38, Jonathan Wiltshire wrote: [...] > > > > 2nd December > > > > 9th December (but preferably earlier, or we start gradually > > > > extending > > > > the cycle) > > > > > > Those both look ok to me. > > > > Did we make a decision yet? Both still look OK for me, but my > > tester > > helpers are asking! > > I believe we still need ftp-master and press confirmation, but I've > been failing at poking. Despite the fact that it's stretching things, in this instance I'd prefer the 9th, as it means we're not having to deal with the freeze over miniconf weekend. I'll get announcements for that out over the next couple of days. Regards, Adam
Re: Scheduling 9.3
Hi all El 15/11/17 a las 19:30, Steve McIntyre escribió: > On Wed, Oct 25, 2017 at 05:00:16PM +0100, Adam Barratt wrote: >> On 2017-09-24 17:38, Jonathan Wiltshire wrote: >>> Hi, >>> >>> Our target for 9.3 and 8.10 is the first weekend in December (this >>> happily >>> makes the following target the beginning of February, avoiding the >>> festive >>> season). >>> >>> Accordingly I'm looking at one of: >> [...] >>> 2nd December >>> 9th December (but preferably earlier, or we start gradually extending >>> the cycle) >> Publicity team is available both weekends. Cheers -- Laura Arjona Reina https://wiki.debian.org/LauraArjona
Re: Scheduling 9.3
On Thu, 2017-11-16 at 08:02 +, Adam D. Barratt wrote: > I believe we still need ftp-master and press confirmation, but I've > been failing at poking. Either of 2017-12-02 or 2017-12-09 should be fine for me. Ansgar
Re: Scheduling 9.3
On 2017-11-15 18:30, Steve McIntyre wrote: On Wed, Oct 25, 2017 at 05:00:16PM +0100, Adam Barratt wrote: On 2017-09-24 17:38, Jonathan Wiltshire wrote: Hi, Our target for 9.3 and 8.10 is the first weekend in December (this happily makes the following target the beginning of February, avoiding the festive season). Accordingly I'm looking at one of: [...] 2nd December 9th December (but preferably earlier, or we start gradually extending the cycle) Those both look ok to me. Did we make a decision yet? Both still look OK for me, but my tester helpers are asking! I believe we still need ftp-master and press confirmation, but I've been failing at poking. *poke* Regards, Adam
Re: Scheduling 9.3
On Wed, Oct 25, 2017 at 05:00:16PM +0100, Adam Barratt wrote: >On 2017-09-24 17:38, Jonathan Wiltshire wrote: >> Hi, >> >> Our target for 9.3 and 8.10 is the first weekend in December (this >> happily >> makes the following target the beginning of February, avoiding the >> festive >> season). >> >> Accordingly I'm looking at one of: >[...] >> 2nd December >> 9th December (but preferably earlier, or we start gradually extending >> the cycle) > >Those both look ok to me. Did we make a decision yet? Both still look OK for me, but my tester helpers are asking! -- Steve McIntyre, Cambridge, UK.st...@einval.com < sladen> I actually stayed in a hotel and arrived to find a post-it note stuck to the mini-bar saying "Paul: This fridge and fittings are the correct way around and do not need altering"
Re: Scheduling 9.3
On 2017-09-24 17:38, Jonathan Wiltshire wrote: Hi, Our target for 9.3 and 8.10 is the first weekend in December (this happily makes the following target the beginning of February, avoiding the festive season). Accordingly I'm looking at one of: [...] 2nd December 9th December (but preferably earlier, or we start gradually extending the cycle) Those both look ok to me. Regards, Adam
Re: Scheduling 9.3
On Sun, Sep 24, 2017 at 05:38:51PM +0100, Jonathan Wiltshire wrote: >Hi, > >Our target for 9.3 and 8.10 is the first weekend in December (this happily >makes the following target the beginning of February, avoiding the festive >season). > >Accordingly I'm looking at one of: > >25th November >2nd December >9th December (but preferably earlier, or we start gradually extending > the cycle) > >Please advise your availability. The 25th is really difficult with the Cambridge mini-debconf that weekend, but the other two should be fine. -- Steve McIntyre, Cambridge, UK.st...@einval.com "I suspect most samba developers are already technically insane... Of course, since many of them are Australians, you can't tell." -- Linus Torvalds
Re: Scheduling 9.3
On 2017-09-24 17:38, Jonathan Wiltshire wrote: Accordingly I'm looking at one of: 25th November 2nd December 9th December (but preferably earlier, or we start gradually extending the cycle) Of course the 25th would be a terrible choice and I should have realised that; that leaves the other two. Thanks, -- Jonathan Wiltshire j...@debian.org Debian Developer http://people.debian.org/~jmw 4096R: 0xD3524C51 / 0A55 B7C5 1223 3942 86EC 74C3 5394 479D D352 4C51 SaaS == Saunas as a Service broonie, more like Sauna as additional Storage