[Orgmode] Org-depends: schedule X days after last completion

2010-02-20 Thread Nathaniel Flath
Hello,
using the org-depends package, is there any way to set the next task to be
scheduled a certain number of days after the current one is finished?

Thanks,
Nathaniel Flath
___
Emacs-orgmode mailing list
Please use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode


Re: [Orgmode] Org-depends: schedule X days after last completion

2010-02-20 Thread Manish
On Sat, Feb 20, 2010 at 11:28 PM, Nathaniel Flath wrote:
 Hello, using the org-depends package, is there any way to set
 the next task to be scheduled a certain number of days after
 the current one is finished?

not at the moment.  though one can visualize the TRIGGER property
chain-siblings-scheduled to be like chain-siblings-scheduled(x) where
x is the number of days to be added to the CLOSED time of the previous
entry to compute new SCHEDULED time.  wish i knew sufficient elisp.

-- 
manish


___
Emacs-orgmode mailing list
Please use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode