[OE-core] Yocto Project Status WW50`21

2021-12-14 Thread Stephen Jolley
Current Dev Position: YP 3.5 M1

Next Deadline: 6th Dec. 2021 YP 3.5 M1 build

 

Next Team Meetings:

*   Bug Triage meeting Thursday Dec. 16th at 7:30am PDT (

https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*   Monthly Project Meeting Tuesday Jan. 4th at 8am PDT (

https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09
 )
*   Weekly Engineering Sync Tuesday Dec. 14th at 8am PDT (

https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09
 )
*   Twitch -  See https://www.twitch.tv/theyoctojester

 

Key Status/Updates:

*   YP 3.5 M1 is in QA
*   YP 3.1.13 is due to build this week
*   We have maintenance to the autobuilder planned to fit SSDs to speed
up IO and update the host distros to more modern equivalents. If parts
arrive as planned, this is scheduled for next week (20th-24th) and the
autobuilder will be unavailable during the work. There may be bring up
issues with the new distros.
*   There were significant improvements in patch metrics this week with
large drops in both patches in the pending state and overlap number of
patches. Thanks to everyone who contributed to that!
*   As part of patch cleanup, some changes were made which could impact
other layers or our spectrum of support. The libtool prefix patches were
dropped as the need was largely obsolete by recipe specific sysroots,
hosttools and other developments and this may mean patches in other layers
can be dropped too. Some non-upstream invasive mips and sh4 patches were
dropped as they were either obsolete or there were less invasive ways to
handle them. 
*   CVE metrics improved this week with drops in open CVEs for both
dunfull and master.
*   Intermittent issues continue to rise and help is very much welcome
on these issues. You can see the list of failures we're continuing to see by
searching for the "AB-INT" tag in bugzilla:

https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT

 

Ways to contribute:

*   There are bugs identified as possible for newcomers to the project:

https://wiki.yoctoproject.org/wiki/Newcomers
*   There are bugs that are currently unassigned for YP 3.5. See:

https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.5_Unassigned_Enhan
cements.2FBugs
*   We'd welcome new maintainers for recipes in OE-Core. Please see the
list at:

http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/main
tainers.inc and discuss with the existing maintainer, or ask on the OE-Core
mailing list. We will likely move a chunk of these to "Unassigned" soon to
help facilitate this.

 

YP 3.5 Milestone Dates:

*   YP 3.5 M1 in QA
*   YP 3.5 M1 Release date 2021/12/17
*   YP 3.5 M2 build date 2022/01/10
*   YP 3.5 M2 Release date 2022/1/21
*   YP 3.5 M3 build date 2022/2/21
*   YP 3.5 M3 Release date 2022/03/04
*   YP 3.5 M4 build date 2022/04/04
*   YP 3.5 M4 Release date 2022/04/29

 

Upcoming dot releases:

*   YP 3.4.1  is released
*   YP 3.1.13 build date 2021/12/13
*   YP 3.1.13 Release date 2021/12/22
*   YP 3.1.14 build date 2022/01/24
*   YP 3.1.14 Release date 2022/02/04
*   YP 3.4.2 build date 2022/02/07
*   YP 3.4.2 Release date 2022/02/18
*   YP 3.3.5 build date 2022/02/14
*   YP 3.3.5 Release date 2022/02/25
*   YP 3.1.15 build date 2022/03/14
*   YP 3.1.15 Release date 2022/03/25
*   YP 3.4.3 build date 2022/03/21
*   YP 3.4.3 Release date 2022/04/01
*   YP 3.3.6 build date 2022/03/28
*   YP 3.3.6 Release date 2022/04/08
*   YP 3.1.16 build date 2022/04/25
*   YP 3.1.16 Release date 2022/05/06

 

Tracking Metrics:

*   WDD 2633 (last week 2583) (

https://wiki.yoctoproject.org/charts/combo.html)
*   OE-Core/Poky Patch Metrics

*   Total patches found: 1225 (last week 1272)
*   Patches in the Pending State: 349 (28%) [last week 400 (31%)]

 

The Yocto Project's technical governance is through its Technical Steering
Committee, more information is available at:

 
https://wiki.yoctoproject.org/wiki/TSC

 

The Status reports are now stored on the wiki at:

https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you'd like to see on this
weekly status update, let 

[OE-core] Yocto Project Status WW50

2016-12-05 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1

Next Deadline: YP 2.3 M1 by Dec. 12, 2016


SWAT team rotation: Anibal -> Tracy

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

*We're now coming to the end of the M1 development period with it 
closing next Monday.

*The recipe specific sysroot patchset has been updated with a number of 
the key issues being addressed.

*Patches are being merged but we're continue to struggle to track down 
which patches in testing are causing which failures which does slow down the 
overall merge progress. The work Ross has been doing here is much appreciated. 
We have seen many recipe upgrades being merged.

*Performance of bitbake on systems with large numbers of cores appears 
to have bottlenecks in bitbake-worker. One patch has already merged for this 
and there are some further patches pending. Python3 appears to have made this 
issue worse.

*The monthly tech meeting is tomorrow at 8am PST.  US Phone: 
8007302996/9139049836, Bridge: 2705751


Proposed upcoming dot releases:

YP 2.0.3 Release by Dec. 9, 2016

YP 2.2.1 Release by Jan. 20, 2017

YP 2.1.3 Release by May. 19, 2017


Key YP 2.3 Dates:

YP 2.3 M1 Cutoff is Dec. 12, 2016

YP 2.3 M1 Release is Dec. 23, 2016

YP 2.3 M2 Cutoff is Jan. 23, 2017

YP 2.3 M2 Release is Feb. 3, 2017

YP 2.3 M3 Cutoff is Feb 27, 2017

YP 2.3 M3 Release is Mar. 10, 2017

YP 2.3 M4 Cutoff is April 3, 2017

YP 2.3 M4 Release is April 28, 2017


Tracking Metrics:

WDD 2507 (last week 2552)

(https://wiki.yoctoproject.org/charts/combo.html)


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features


[If anyone has suggestions for other information you'd like to see on this 
weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:(503) 712-0534
*Cell:   (208) 244-4460
* Email:stephen.k.jol...@intel.com

-- 
___
Openembedded-core mailing list
Openembedded-core@lists.openembedded.org
http://lists.openembedded.org/mailman/listinfo/openembedded-core


[OE-core] Yocto Project Status WW50

2015-12-11 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M2

Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon 
GMT


SWAT team rotation: Beth -> Saul

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

* M1 release has been build and passed to QA

* Patch stabilization continues to be a problem, many patches causing 
failures which slow down patch merging

* Various things missed M1, primarily due to it being a short milestone 
because of the overrun of 2.0 stabilization

* Some key changes upcoming, automation of -dbg packages, tinfoil2 and 
default to memory resident bitbake, perhaps default of using uninative for 
poky, require expansion parameter to getVar, gobject introspection, libexecdir 
changes, musl integration.


Key YP 2.1 Dates:

YP 2.1 M1 Target release date is December 24, 2015

YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT

YP 2.1 M2 Target release date is February 12, 2016

YP 2.1 M3 Cutoff (Feature Freeze) date is February 29, 2016 noon GMT

YP 2.1 M3 Target release date is March 18, 2016

YP 2.1 M4 / Final Cutoff: March 28, 2016 noon GMT - Stabilization only 
milestone.

YP 2.1 Final Release Target: April 29, 2016


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.1_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.1_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.1_Features


Tracking Metrics:

WDD 2300 (last week 2228)

(https://wiki.yoctoproject.org/charts/combo.html)

[If anyone has suggestions for other information you'd like to see on this 
weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:  (503) 712-0534
*Cell:(208) 244-4460