Re: Milestone moved: M1 is now Aug 11, 2014

2014-07-31 Thread Kevin Rushforth
As a reminder, we will be in rampdown mode for the week prior to the Aug 
11 M1 milestone build. This means that starting on Monday, Aug 4, you 
need an additional +1 from one of the leads. We are likely to be more 
liberal about what goes in this next week since this is the first 
milestone, and because we don't yet have promoted builds of 8u40, and 
are still busily working on features.


See https://wiki.openjdk.java.net/display/OpenJFX/Sanity+Testing for 
weekly freeze and milestone rampdown rules.


-- Kevin  Steve


Stephen F Northover wrote:

Hi all,

This week (July 28) is the week before M1 milestone (Aug 4) so we 
should be ramping down (ie. extra +1 restrictions for committing code, 
more/better testing, etc.).  Since this is the first milestone for 
8u40 and there important API deadlines, I spoke with Kevin and we 
agreed to move M1 back a week to Aug 11 to give us a bit more time 
before the ramp down.


I have updated the wiki: 
https://wiki.openjdk.java.net/display/OpenJFX/8u40


Steve


Milestone moved: M1 is now Aug 11, 2014

2014-07-28 Thread Stephen F Northover

Hi all,

This week (July 28) is the week before M1 milestone (Aug 4) so we should 
be ramping down (ie. extra +1 restrictions for committing code, 
more/better testing, etc.).  Since this is the first milestone for 8u40 
and there important API deadlines, I spoke with Kevin and we agreed to 
move M1 back a week to Aug 11 to give us a bit more time before the ramp 
down.


I have updated the wiki: https://wiki.openjdk.java.net/display/OpenJFX/8u40

Steve