Hi again,
Could check the following info:
1) Production order Inquiries Production postings :
How many Good and Error quantities were posted in Report as finished
journals?
2) Production order Inventory Transactions :
What quantity was posted in transactions with status Received?
Please also
hi nitesh ranjain
to solve your issue you should used to Validation at variable ,when choose
textlite show the colors blue and green .
writhe the conditions in the validation .
best regards
Mohammad Idais
Nitesh Ranjan [EMAIL PROTECTED] wrote:
For this you need to create
Hi am working on AX4.0 sp1.My client is into control panel
manufacuturing.His business process is Make To Order.If any knows
about make to order concept in AX how to configure...Plz let me know
Regards,
Imme
Hi,
We are implementing AX-3.0 in a company, they need depreciation
schedule as per indian company law schedule IV format, in indian
localization of Axapta Depreciation schedule is available, but datas
from the fixed asset master are not picked up, could anyone guide me
setting up and
We have quite a few clients with the same issue. So we developed a AX Tree
Dim product that works with an Excel Reporter. Please go to the link below
if you are interested.
http://www.xlreporter.com
Jim Hummer
Senior Consultant
From: prasanna govindan [EMAIL PROTECTED]
Reply-To:
Does anyone have any experiance with the BOM rollup process as it
pertains to manufactured sub assemblies?
I'd like to know if there's a way to display the Mat'l , labor and OH
costs for all Mfg items when any one Mfg item is completed.
Thanks.
Thank you for your reply..
One more question in (1).
If the query field(virtual field) is get from the table method. How
to do it.
Thanks
--- In Axapta-Knowledge-Village@yahoogroups.com, Steeve Gilbert
[EMAIL PROTECTED] wrote:
Hi,
1. You can get range value with this if you set range on
Someone mentioned to me that there's a white paper on costing in
partner source someplace. They think it is a resource to learn how to
see the materials labor and overhead costs associated with each sub
assembly owned by the parent as the parent is being completed.
Any thoughts?
Hi,
I'm facing the following error message :
Calculating Production : Production Cannot be post-adjusted
This happend when user tried to end the job.
Initially I suspected the problem lies on Report as Finished journal posted
with zero Qty. I guess they did the following sequence of steps :
1.
9 matches
Mail list logo