I did an MRP run for a single sales order line and firmed the 2 planned production orders MRP suggested using the futures date (since the sales order is requested inside of the lead time). All the dates are correct, but as soon as I re-run MRP I'm getting action messages to advance those two orders I just firmed, even though the operation scheduling makes it obvious that the component order cannot be completed in time to achieve this (the futures date from MRP already told me the earliest finish date).
Am I missing a setting that will let it still consider the futures date on future runs? In my mind I shouldn't be seeing action messages re- running MRP after accepting its suggestions (there are no other orders in the system except the sales order and 2 firmed production orders). The only time I should see an action message under this case is if the component order has production reported on it and it becomes possible to move up the start of the final assembly order. None of the parameters under Master Planning->Setup->Plans->Master Plans change the result. Thanks in advance for any help. ------------------------ Yahoo! Groups Sponsor --------------------~--> Has someone you know been affected by illness or disease? Network for Good is THE place to support health awareness efforts! http://us.click.yahoo.com/Rcy2bD/UOnJAA/cosFAA/kGEolB/TM --------------------------------------------------------------------~-> Sharing the knowledge on Axapta. Yahoo! Groups Links <*> To visit your group on the web, go to: http://groups.yahoo.com/group/Axapta-Knowledge-Village/ <*> To unsubscribe from this group, send an email to: [EMAIL PROTECTED] <*> Your use of Yahoo! Groups is subject to: http://docs.yahoo.com/info/terms/