Hello All; In the plant where Axapta is used, there are 3 shifts - 1st, 2nd and 3rd. We are trying to schedule people who assemble equipment. An assembly operation usually takes more hours than can be accomplished in a single shift. Therefore, people on the next shift take over and continue assembling the equipment.
I have a single work center group set up that contains individual work centers. The work centers are of type 'Human Resource' and represent each of the assembly people. I also have three calendars set up - one for each shift. The work centers contain the appropriate calendar for the shift the person works. Whenever I run job scheduling for the production order it always uses a single work center and schedules it out for multiple consecutive days, scheduling only one shift per day. I want it to schedule all three shifts in a single day - the first shift work center, then the second shift work center, then the third shift work center. After a single day of all three shifts having been scheduled, then it should begin the process again for the next day until all of the demand is satisfied. In the route, I have set the 'Quantity of Work Centers' field to 3 and it still does not schedule consecutive shifts per day. In fact, I get an interesting error. Any thoughts? Thanks in advance, Michael Spadaro Clients First Business Solutions ------------------------ Yahoo! Groups Sponsor --------------------~--> Put more honey in your pocket. (money matters made easy). http://us.click.yahoo.com/r7D80C/dlQLAA/cosFAA/kGEolB/TM --------------------------------------------------------------------~-> Sharing the knowledge on Axapta. Yahoo! Groups Links <*> To visit your group on the web, go to: http://groups.yahoo.com/group/Axapta-Knowledge-Village/ <*> To unsubscribe from this group, send an email to: [EMAIL PROTECTED] <*> Your use of Yahoo! Groups is subject to: http://docs.yahoo.com/info/terms/