hi
 
There are 3 combinations
 
1. You have setup a specified a static plan and a dynamic plan on the master 
planning parameters:
 
in this case you can run net change only for the dynamic plan.
 
2. If you have setup the same plan for static as well as dynamic then u can run 
net change for the dynamic plan (which is the same as static plan)
 
3. If you have not setup dynamic plan then you cannot run net change at all. 
the update type in this case is internally changed to regneration.
 
regards
 
harry

________________________________

From: Axapta-Knowledge-Village@yahoogroups.com on behalf of soniahadi987
Sent: Wed 4/12/2006 1:33 PM
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: [Axapta-Knowledge-Village] net change method



Hello All,
The function to run Net Change, net change minimize methods are
disabled while trying to run Master scheduling, I can run only
regeneration method.
Any body knows the reason behind it.

Thanks

Sonia








Sharing the knowledge on Axapta.
Visit www.frappr.com/axapta for axapta friends.
Yahoo! Groups Links










[Non-text portions of this message have been removed]



Sharing the knowledge on Axapta.
Visit www.frappr.com/axapta for axapta friends. 
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/Axapta-Knowledge-Village/

<*> To unsubscribe from this group, send an email to:
    [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/
 


Reply via email to