Hi Austin,
since you want to use the same semantics as for deadlines, i.e. the
same warning period etc, this really is a psychological issue :-)
It is trouble to implement a new keyword or number of keywords. New
commands needed to insert this new keyowrd, for example, and many
regular
Hi all!
Currently we can use the DEADLINE keyword to indicate a target date for
an item to be finished. By my way of thinking, deadlines make sense for
externally imposed constraints. I also try to set goals for myself for
when an item will be completed. These are softer than deadlines, but
I