1.9.1 checklist

2009-05-26 Thread Andy Wingo
Hey folks! So, IMO we need to start pushing towards a release. How about getting a 1.9.1 out soon? My feeling is that the current feature set in master is ready for a release. We could just distcheck and that's that. (I tried distcheck today at work, and it worked fine.) But there are a few feat

Re: 1.9.1 checklist

2009-05-26 Thread Julian Graham
Hi Andy, >  R6RS library support: >   No code yet. Julian? :-) Yeah... As I mentioned on IRC, I punted temporarily on that while I was rewriting the parser for my CSS library. Just yesterday, though, I started doing some initial work towards adding version information to modules and the module-

Re: 1.9.1 checklist

2009-05-26 Thread Mike Gran
> Hey folks! > > So, IMO we need to start pushing towards a release. How about getting a > 1.9.1 out soon? > > Unicode: >Code shaping up, needs review and R6RS-libs. Unclear how much will be >in shape for 2.0. Acceptable to ship with only the finished parts. > The big steps to hit a be

Re: 1.9.1 checklist

2009-05-26 Thread Ludovic Courtès
Hello Andy! This all sounds like an excellent plan to me! In practice, that would mean making the first release on June 15th, right? Ludo'.

Re: 1.9.1 checklist

2009-05-27 Thread Neil Jerram
Andy Wingo writes: > My proposal would be a time-based release schedule. We can decide the > Guile 2.0 release date now, and three or four micro releases before > then. > > August in Europe is rather slow, and September people are catching up, > so I would propose October 15 for Guile 2.0. Then

Re: 1.9.1 checklist

2009-05-27 Thread Neil Jerram
Andy Wingo writes: > (I tried distcheck today at work, and it worked fine.) That's curious. It's failing at the moment for me (as I mentioned in another email). I guess my action to look into that failure then. Neil

Re: 1.9.1 checklist

2009-05-28 Thread Ludovic Courtès
Hello! Neil Jerram writes: > As regards the mechanics of releasing: recently Ludovic has handled > that. Will you be OK to continue doing the releases to Andy's > proposed schedule, Ludo; or Andy are you proposing to handle the > release process yourself instead? FWIW, I'm happy to keep releas

Re: 1.9.1 checklist

2009-05-28 Thread Andy Wingo
On Wed 27 May 2009 01:48, l...@gnu.org (Ludovic Courtès) writes: > This all sounds like an excellent plan to me! Excellent! I love it when a plan comes together! > In practice, that would mean making the first release on June 15th, > right? Yes. We probably would need the longer freeze (of 10

Re: 1.9.1 checklist

2009-05-28 Thread Andy Wingo
Hello! On Thu 28 May 2009 15:01, l...@gnu.org (Ludovic Courtès) writes: > For 2.0, though, I think it may be wiser to let Andy take care of it, if > he wants to: he's been more responsive than me, and he's the 2.x guy > after all. ;-) Andy: what do you think? > > (I'm happy to take care of it i

Re: 1.9.1 checklist

2009-05-28 Thread Andy Wingo
On Thu 28 May 2009 00:15, Neil Jerram writes: > Andy Wingo writes: >> (I tried distcheck today at work, and it worked fine.) > > That's curious. It's failing at the moment for me (as I mentioned in > another email). I guess my action to look into that failure then. Hm, is failing for me here

Re: 1.9.1 checklist

2009-05-28 Thread Ludovic Courtès
Hi! Andy Wingo writes: > Yes. We probably would need the longer freeze (of 10 days) to get the > docs and NEWS and things in shape for this one, meaning no new code > should go in between the 5th and the 15th, just testing and doc updates > and regression fixes. Sound good to you? Yes, but...

Re: 1.9.1 checklist

2009-05-28 Thread Ludovic Courtès
Andy Wingo writes: > To be honest, I'd rather not [have to] handle release mechanics -- while > I can do it, I would be more than happy for you to keep handling > releases, Ludovic. Fine with me. I'll do my best to be available on the 14th-15th of each month, then. > Or perhaps we should share

Re: 1.9.1 checklist

2009-05-28 Thread Ludovic Courtès
Hi, Andy Wingo writes: > Here are the features that I know of, in no particular order: > > BDW-GC: >Looks really promising. All the code is there. Unknown implications, >needs lots more testing. Needs to see at least one and hopefully two >micro releases. (1.9.x) > > R6RS library s

Re: 1.9.1 checklist

2009-05-29 Thread Andy Wingo
On Thu 28 May 2009 23:27, l...@gnu.org (Ludovic Courtès) writes: > There's one more item: > > licensing: > Switch to LGPLv3+, as was decided some time ago. Check the license > headers of new code and code inherited from Guile-VM. Good point. I switched over the headers for VM .c code t