[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-16 Thread Dag Andersen
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #12 from Dag Andersen --- Yes, new functionality. Resource groups are now optional and it is possible to assign resource to multiple groups. They can thus be used for both skills based and organizational groups. The resource group editor

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-15 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #11 from cqu...@arcor.de --- Well, maybe I see something weird, but I don't know whether this is due to my source build or not: it looks like now it is possible to assign a resource to several resource groups. I guess that is a new feature.

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-15 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #10 from cqu...@arcor.de --- I have managed to run it from source and indeed the bugs have been fixed! Thanks! -- You are receiving this mail because: You are watching all bug changes.

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-15 Thread Dag Andersen
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #9 from Dag Andersen --- (In reply to cquike from comment #8) > That's nice that it has been fixed! > Is there a way to test this using some package? Or source compilation is > currently the only option? Source is only option unless you

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-15 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #8 from cqu...@arcor.de --- That's nice that it has been fixed! Is there a way to test this using some package? Or source compilation is currently the only option? Thanks! -- You are receiving this mail because: You are watching all bug

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-15 Thread Dag Andersen
https://bugs.kde.org/show_bug.cgi?id=449786 Dag Andersen changed: What|Removed |Added Resolution|--- |FIXED Latest Commit|

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-09 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #6 from cqu...@arcor.de --- Created attachment 146505 --> https://bugs.kde.org/attachment.cgi?id=146505=edit project plan -- You are receiving this mail because: You are watching all bug changes.

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-09 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #5 from cqu...@arcor.de --- Hi, I have checked the scheduling logs and there are only Info messages, both with the Network Scheduler and the TJ Scheduler. I attach here my project file, hopefully you can reproduce the error that way. --

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-09 Thread Dag Andersen
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #4 from Dag Andersen --- Confirm that total hours is not updated in "Resource assignments", probably changes are not picked up correctly by the view. I cannot reproduce the problem with wrong total here. I get 29.6 for resource 1 and 50.4

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-08 Thread Dag Andersen
https://bugs.kde.org/show_bug.cgi?id=449786 Dag Andersen changed: What|Removed |Added Status|REPORTED|CONFIRMED Ever confirmed|0

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-08 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 cqu...@arcor.de changed: What|Removed |Added Attachment #146440|Task (80 hours) |Calendars description|

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-08 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #3 from cqu...@arcor.de --- Created attachment 146442 --> https://bugs.kde.org/attachment.cgi?id=146442=edit Wrong Total hours -- You are receiving this mail because: You are watching all bug changes.

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-08 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #2 from cqu...@arcor.de --- Created attachment 146441 --> https://bugs.kde.org/attachment.cgi?id=146441=edit Task (80 hours) -- You are receiving this mail because: You are watching all bug changes.

[calligraplan] [Bug 449786] Total "Resource assignments" are wrong if the resources have different calendars and availability

2022-02-08 Thread bugzilla_noreply
https://bugs.kde.org/show_bug.cgi?id=449786 --- Comment #1 from cqu...@arcor.de --- Created attachment 146440 --> https://bugs.kde.org/attachment.cgi?id=146440=edit Task (80 hours) -- You are receiving this mail because: You are watching all bug changes.