Current Milestones:
|| || Planned|| Estimate || Actual ||
||cp15-rework || 2012-01-06 || 2012-06-23 || 2012-06-24 ||
||a15-lpae-support || 2012-07-13 || 2012-07-20 ||||
||clean-up-kvm-patches ||||||
On 6 July 2012 19:00, Christian Robottom Reis wrote:
> On Fri, Jul 06, 2012 at 05:19:10PM +0100, Peter Maydell wrote:
>> Current Milestones:
>> || || Planned|| Estimate || Actual ||
>> ||cp15-rework || 2012-01-06 || 2012-06-23 || 2012-06-24 ||
>
> W
On Fri, Jul 06, 2012 at 05:19:10PM +0100, Peter Maydell wrote:
> Current Milestones:
> || || Planned|| Estimate || Actual ||
> ||cp15-rework || 2012-01-06 || 2012-06-23 || 2012-06-24 ||
Wow. That's a lot of months off-plan! I like it that you have t
Current Milestones:
|| || Planned|| Estimate || Actual ||
||cp15-rework || 2012-01-06 || 2012-06-23 || 2012-06-24 ||
||a15-lpae-support || 2012-07-13 || 2012-07-13 ||||
||clean-up-kvm-patches ||||||
RAG:
Red:
Amber: OMAP3 patch upstreaming is slower progress than hoped
Green:
Current Milestones:
|| || Planned|| Estimate || Actual ||
||qemu-linaro-2011-07 || 2011-07-21 || 2011-07-21 ||||
Historical Milestones:
||qemu-linaro 2011-04 ||