Hello all,
Power is back and everything seems to be up and running again.
Please let me know, if something is not working as expected.
-Ihsan
> Am 20.02.2019 um 17:40 schrieb ihsan--- via maintainers
> :
>
> Hello all,
>
> Our ISP Solnet has informed, that they to perform some maintenance
Hello all,
Our ISP Solnet has informed, that they to perform some maintenance on their
datacenter power. Unfortunately they have to turn of the complete power of
their datacenter.
Our mail and web server will be therefore offline on the 21st February between
9:00 - 12:00 CEST.
-Ihsan
--
Hi folks,
we are currently experiencing an unplanned power outage in our datacenter.
It looks like the UPS failed in a way which prevented the automatic bypass to
work.
We bypassed it now manually and will restart all machines during the day.
The buildfarm, buildbot and catalog generation