Dear all,

I'm working on network reduction problem, in which I moved loads,all
renewable generation and conventional power plants from 110 KV buses to
respective connected branches (220 KV or  380 KV). I have modeled network
such that distribution of load or generation will be 50 % if more than one
branches are connected to 110 KV bus. And after I made branch status 0 of
 the branches which are connected to 110 KV buses.  When I checked for
islands (case_info)  in my file  I found 2 islands and 336 isolated buses.
Also I verified it by [group, isolated]=find_island ('myfile'). My question
is how to get a full system? I found three buses where generation and load
does exist and are completely isolated  and two islands. Also I tried to
get full system by putting dummy branches to connect isolated buses and a
small island but i'm not sure how to select branch parameters so that
problem will be feasible.

Thanks and regards
Mirish Thakur