sir
actually I want the customers to curtail the load by providing
incentives for them.If they donot curtail I want to pose penalties for them
using an Ieee 14 bus system.
On Fri, May 13, 2016 at 9:34 AM, Carlos E Murillo-Sanchez <
ce.murillosanc...@gmail.com> wrote:
> Dear Mounika:
>
> We nee
Dear Mounika:
We need to understand the nature of your question. It seems as if you
might be trying to force a two-stage decision problem onto the framework
of a single-stage one. Hence Ray's answer. Please ellucidate.
carlos.
Mounika Vanjarapu wrote:
sir
can we pose penalties for th
can you tell me the approach for posing penalties.
On Thu, May 12, 2016 at 10:43 PM, Ray Zimmerman wrote:
> Probably.
>
> > On May 12, 2016, at 12:16 PM, Mounika Vanjarapu <
> mounikavanjar...@gmail.com> wrote:
> >
> > sir
> >can we pose penalties for the customers who don't curtail the load
It appears that you have no reactive generation capacity to meet any reactive
demand.
Ray
>> case_info('rede_teste')
Checking connectivity ... single fully connected network
Elapsed time is 0.007586 seconds.
Probably.
> On May 12, 2016, at 12:16 PM, Mounika Vanjarapu
> wrote:
>
> sir
>can we pose penalties for the customers who don't curtail the load using
> matpower.
You should be able to formulate your problem as an OPF. Simply treat each DG as
a generator with sufficiently large PMAX and zero cost. And set the voltage
limits appropriately (seems you want to base them the original power flow
solution). What I’m not sure is how you intend to set up the load
sir
can we pose penalties for the customers who don't curtail the load using
matpower.
Dear all,
I'm trying to simulate the operation of a microgrid functioning in islanded
mode composed by 15 photovoltaic (PV) micro-generation units, therefore I
classified all the buses with generation as PQ, since solar panels only produce
active power. I set that, to all the generators:
PG =
Dear Matpower users,
So I will describe my problem so that you can tell me if this can be done
in matpower.
I have a medium voltage rural grid with 15 buses (14 PQ and 1 slack) and I
want to use OPF for maximizing the DG capacity penetration. (for simplicity
lets discuss only the case of unity po