[Pharo-project] Preparing 1.4 beta

2012-01-12 Thread Stéphane Ducasse
Hi since we will not have OPAL as preview in 1.4 and we do not need to change the refactoring engine code, we will unload AST and RBEngine package from the system and start to pass in 1.4 beta probably at the end of the month. One idea was that we could have decent tools to work on the core but

Re: [Pharo-project] Preparing 1.4 beta

2012-01-12 Thread Luc Fabresse
2012/1/12 Stéphane Ducasse > Hi > > since we will not have OPAL as preview in 1.4 and we do not need to change > the refactoring engine > code, we will unload AST and RBEngine package from the system and start to > pass in 1.4 beta probably at the end of the month. One idea was that we > could ha

Re: [Pharo-project] Preparing 1.4 beta

2012-01-12 Thread Stéphane Ducasse
We would like to have one month beta, and one month release candidate. so beta first of February, release candidate first of March. We would open 1.5alpha either in rc or at the end of March. Stef On Jan 13, 2012, at 7:37 AM, Luc Fabresse wrote: > > > 2012/1/12 Stéphane Ducasse > Hi > > sin

Re: [Pharo-project] Preparing 1.4 beta

2012-01-12 Thread Norbert Hartl
Very good idea to release what we have and continue with open stuff in 1.5. Feels just right! Norbert Am 12.01.2012 um 21:54 schrieb Stéphane Ducasse : > Hi > > since we will not have OPAL as preview in 1.4 and we do not need to change > the refactoring engine > code, we will unload AST and

Re: [Pharo-project] Preparing 1.4 beta

2012-01-13 Thread Stéphane Ducasse
thanks. May be I will add SystemAnnouncement and RPackage since this is stable. We will check if we can push or not in 1.4 the clean of the eventBuff. Stef > Very good idea to release what we have and continue with open stuff in 1.5. > Feels just right! > > Norbert > > > > Am 12.01.2012 um 2

Re: [Pharo-project] Preparing 1.4 beta

2012-01-13 Thread Luc Fabresse
2012/1/13 Norbert Hartl > Very good idea to release what we have and continue with open stuff in > 1.5. Feels just right! > yes! Luc > > Norbert > > > > Am 12.01.2012 um 21:54 schrieb Stéphane Ducasse >: > > > Hi > > > > since we will not have OPAL as preview in 1.4 and we do not need to >

Re: [Pharo-project] Preparing 1.4 beta

2012-01-13 Thread Henrik Johansen
On Jan 13, 2012, at 1:18 44PM, Stéphane Ducasse wrote: > thanks. May be I will add SystemAnnouncement and RPackage since this is > stable. > We will check if we can push or not in 1.4 the clean of the eventBuff. > > Stef See issue 5172 - 5174 for my comments. TLDR; I don't think it's a good i

Re: [Pharo-project] Preparing 1.4 beta

2012-01-13 Thread Stéphane Ducasse
On Jan 13, 2012, at 4:09 PM, Henrik Johansen wrote: > > On Jan 13, 2012, at 1:18 44PM, Stéphane Ducasse wrote: > >> thanks. May be I will add SystemAnnouncement and RPackage since this is >> stable. >> We will check if we can push or not in 1.4 the clean of the eventBuff. >> >> Stef > > See

Re: [Pharo-project] Preparing 1.4 beta

2012-01-13 Thread Henrik Johansen
On Jan 13, 2012, at 9:44 30PM, Stéphane Ducasse wrote: > >> (but have a backwards-compatible external package) > > I think that it will be difficult enough to swap the two events notification > systems > and that we will not make a backward compatible package. I think that for > migrating the

Re: [Pharo-project] Preparing 1.4 beta

2012-01-15 Thread Stéphane Ducasse
On Jan 13, 2012, at 11:14 PM, Henrik Johansen wrote: > > On Jan 13, 2012, at 9:44 30PM, Stéphane Ducasse wrote: > >> >>> (but have a backwards-compatible external package) >> >> I think that it will be difficult enough to swap the two events notification >> systems >> and that we will not ma