Re: [RE-wrenches] Utility Side Feed In and Disconnects (was "Line Side")

2009-03-15 Thread Drake Chamberlin
If I understand the issue correctly, the inspector is requiring the PV disconnect for the utility feed to be treated as a service. By the definition in Article 100, it can not be a service, and therefore should not be subject to the rules of a service. The definition is quoted below: Service

Re: [RE-wrenches] Utility Side Feed In and Disconnects (was "Line Side")

2009-03-15 Thread Wayne Irwin
Thanks Matt! You bring up some very strong points. I will see if I can get the local AHJ to see the light. I won't expect any change in his interpretation, but I'm sitting here with the code book and it seems pretty clear to me. I have to at least try. I'll let you know how it goes. Thank

Re: [RE-wrenches] Using the Archive (was Sample Power PurchaseAgreements)

2009-03-15 Thread Michael Welch
Hi gang. Even though the other day I treated lightly Peter's message about how to search the archives, here is some info I should have included at the time. The list's archives are incomplete, and the old Topica archive search is still broken so that  is not an option. Yes, I have all back messag

Re: [RE-wrenches] Utility Side Feed In and Disconnects (was "Line Side")

2009-03-15 Thread Matt Lafferty
Hi Wayne, Grouping is a gray area in the NEC. Subject to the discretion and interpretation of the AHJ. Always has been since the concept of grouping was established. Certain conditions and occupancy classifications may allow different interpretations. Article 230 provides requirements for s

Re: [RE-wrenches] Using the Archive (was Sample Power PurchaseAgreements)

2009-03-15 Thread ASAP POWER! 2
By default, I had taken up Michael's suggestion from topica daze that the best way to make use of an archive was to use your own. Just keep posts you know you may have interest in, in a special folder. I did a find in my WRENCH outlook folder and found Antony's message as one of four I had diy-ar

Re: [RE-wrenches] Silent Power Inverter

2009-03-15 Thread Glenn Burt
Is it UL listed? The spec says 'Designed to meet UL1741 and CSA STD No. 107.1-01' -Glenn Burt _ From: re-wrenches-boun...@lists.re-wrenches.org [mailto:re-wrenches-boun...@lists.re-wrenches.org] On Behalf Of David Katz Sent: Sunday, March 15, 2009 12:34 AM To: al...@positiveenergysola

[RE-wrenches] Using the Archive (was Sample Power Purchase Agreements)

2009-03-15 Thread Joel Davidson
Hello Antony, Thank you very much. How did you find it? Archive searches for PPA and Power Purchase Agreement did not work for me. Joel Davidson - Original Message - From: Antony Tersol To: RE-wrenches Sent: Sunday, March 15, 2009 7:41 AM Subject: [RE-wrenches] Fwd: Sample Pow

[RE-wrenches] Fwd: Sample Power Purchase Agreements

2009-03-15 Thread Antony Tersol
Joel, this the posting you remember? Antony -- Forwarded message -- From: Antony Tersol Date: Wed, Dec 17, 2008 at 11:24 AM Subject: [RE-wrenches] Sample Power Purchase Agreements To: RE-wrenches There is a publication at stoel called Lex Helius, 83 pages. It has two chapters o

Re: [RE-wrenches] Power Purchase Agreements

2009-03-15 Thread roger dixon
If you get info on this, could you forward it on to me as well? Thanks, Roger Dixon Certified Wind Site Assessor Skylands Renewable Energy, LLC 908.337.2057 cell 908.730.6474 fax roger.di...@att.net Note: The information contained in this communication is confidential, may be attorney-client pr