BUDGET OF THE CONSTRUCTION OF SALIGAO CHURCH……………2
                                     

                                             ARTICLE……..II


In  What Respects To The Budget  Of The Works Of Masonry   Item-Wise       

    The foundations and the walls of the Church, Sanctuary, Arcade of the Choir and 
Belfry produce 170 braces of masonry of 300 cubic ‘maos’ each brace. For 
its construction the following material will be used:
12.750 big stones, each one 3 ½ ` maos’  of length, ten thumbs of breadth and 7 
` maos ‘ of thickness @ 40 xerafins =5,100 xerafins.

34 mounds of lime @ 25 xerafins a mound=850 xerafins.

5,000 baskets of mud( of stones) @ ten xerafins a hundred=500 xerafins

1.500 baskets of sweet sand @ 3 xerafins a hundred=45 xerafins.

12 ‘maos’ of coconut jaggery @ 6 xerafins=90 xerafins.

For works of masons and helpers to dig the foundations, its construction and the walls 
regulating 10 xerafins a brace, approximately=1.7000 xerafins.

The Walls in general of the Church, Sanctuary, Arcade of the choir and the Belfry 
which should be constructed with all its mouldings “cimalhas”, columns, 
arcarde, tribunes, vaults and cupolas will produce approximately 425 braces of masonry 
work of 300 cubic ‘ maos’ each brace. For its construction the following 
material will be used.:

9000 big stones and of dimension and price indicated above=3.600 xerafins.
10,000 stones of ‘ maos’ of length, 10 thumbs of breadth and 7 ‘ 
maos’ of thickness @ 33 xerafins a hundred=3.3000 xerafins.
12.000 stones of 2 ½ ‘maos’ of  length, 9 thumbs of breadth and 7  
`maos’ of thickness @ 30 xerafins a hundred=3,6000 xerafins.
5.500 stones of the said length, 14 thumbs of  breadth and 6 ‘ maos’ of 
thickness @ 35 xerafins a hundred=1.925 xerafins.
400 stones of 3 ½ ‘ maos’ in square and 7 thumbs thickness @ 100 xerafins 
a  hundred=400 xerafins.
800 baskets of mud stones idem=800 xerafins.
70 ‘ maos’ of coconut jaggery, idem=420 xerafins.
35 ‘ maos’ of cato, idem=525 xerafins.

For the works of masons and helpers for the perfect execution of all the referred work 
inclusive of red and white “ cafelo “, calculated @ 20 xerafins each 
brace=8.500 xerafins.

The same  for the works of Carpenters for the construction of all unadorned, entering 
into account the wood and all necessary material=500 xerafins.
The walls of the sacristy an the corridor with its foundations and the walls of cement 
mixed (entulho) in total will produce 60 braces of masonry work. For the execution of 
its construction the use of the following material will be necessary;
6.700 stones of 2 ½ ‘ maos’ of length, 9 thumbs of breadth and 7 thumbs of 
 thickness @ 30 xerafins a hundred=2.010 xerafins.
15 “ moios” of chunnam @ 25 xerafins a moi=375 xerafins.
1.200 baskets of mud stones @ 10 xerafins a hundred=120 xerafins.
300 baskets of the  sweet sand @ 3 xerafins  per hundred=9 xerafins.
4 ‘ maos’ of coconut jaggery @ 6 xerafins a ‘ mao’ = 24 
xerafins.
2 ‘ maos’ catho @ 15 xerafins a ‘ mao’=30 xerafins.

Of the works of masons and helpers @ 12 xerafins a brace=720 xerafins.

The staircase of the choir and the steps, for internal doors of the corridor of the 
church can produce 7 braces of work of masonry which sum up to 35 xerafins, each 
brace=245 xerafins.

In short --56.350 stones are used for the Church.
                   7.000 Baskets of mud-stones.
                         34 mounds of lime.
                   2000  baskets of sweet sand .
                   86 ‘ maos’ of coconut jaggery.
                    43 ‘ maos’ of catho
                   150 ‘ moios’ of chunnam..

As years passed by  repairs  and re-construction  with their new budgets followed. 
However the above  mentioned articles and budget is given  here so that the new 
generation of Saligaokars know  about the material used to construct the original 
Church of Mae de Deus—Saligao as well as the amount approved. The original text 
is in Portuguese.
                                                                                   