[scm-migration-dev] very preliminary schedule

2008-02-17 Thread Jim Walker
James Carlson wrote: >> - I need a better understanding of how we'll be doing testing. Will Jim >> Walker be running tests for us, or will the developers being doing all >> the testing? And we need to finalize the test plan. > > We've never had automated testing for these tools (which is rea

[scm-migration-dev] very preliminary schedule

2008-02-12 Thread Mike Kupfer
> "Jim" == James Carlson writes: Jim> I'm not sure what fits in "more stuff TBD," but at a guess, this is Jim> actually "fixing any fall-out from the SFW migration so that ON Jim> doesn't see it." This was a catch-all for items on the task list wiki page, with a SWAG at how long things would

[scm-migration-dev] very preliminary schedule

2008-02-06 Thread James Carlson
Mike Kupfer writes: > - I made a random guess and put down Jim C working 25% on technical > issues. Sounds fair enough. > - Are there things on the list that we don't need to do? I'm willing to > drop items from the list (after discussion), but I'm not willing to > reduce effort estimates

[scm-migration-dev] very preliminary schedule

2008-02-06 Thread Mike Kupfer
Okay, so I put together a very preliminary schedule, which has the tools putback happening in early May. Details are on the project web page: http://www.opensolaris.org/os/project/scm-migration/scm-mig-schedule.pdf Some assumptions: - I'll be working 50% on technical issues and 50% on tech