James Carlson wrote:
>> - I need a better understanding of how we'll be doing testing. Will Jim
>> Walker be running tests for us, or will the developers being doing all
>> the testing? And we need to finalize the test plan.
>
> We've never had automated testing for these tools (which is rea
> "Jim" == James Carlson writes:
Jim> I'm not sure what fits in "more stuff TBD," but at a guess, this is
Jim> actually "fixing any fall-out from the SFW migration so that ON
Jim> doesn't see it."
This was a catch-all for items on the task list wiki page, with a SWAG
at how long things would
Mike Kupfer writes:
> - I made a random guess and put down Jim C working 25% on technical
> issues.
Sounds fair enough.
> - Are there things on the list that we don't need to do? I'm willing to
> drop items from the list (after discussion), but I'm not willing to
> reduce effort estimates
Okay, so I put together a very preliminary schedule, which has the tools
putback happening in early May. Details are on the project web page:
http://www.opensolaris.org/os/project/scm-migration/scm-mig-schedule.pdf
Some assumptions:
- I'll be working 50% on technical issues and 50% on tech