On Dec 26, 2010, at 14:27, Cyril Brulebois wrote:
> Jeremy Huddleston (14/12/2010):
>> I've updated the X.org calendar for the xorg-server-1.9.4 release
>> schedule. […] 1.10.0 is scheduled for release in mid February, so
>> we'll likely have just one mo
Jeremy Huddleston (14/12/2010):
> I've updated the X.org calendar for the xorg-server-1.9.4 release
> schedule. […] 1.10.0 is scheduled for release in mid February, so
> we'll likely have just one more release (1.9.5) in mid march.
Quick question about packaging: What do you
I've updated the X.org calendar for the xorg-server-1.9.4 release schedule.
The 6 week schedule (3/2/1) has been working fairly well, so I'm keeping with
the pattern (but 4/2/1 in this case due to the holiday):
2011.01.07 - 1.9.4rc1
2011.01.21 - 1.9.4rc2 (freeze for regres