Attendees: Armin, Stephen, Saul, Beth, Bruce, Mark, Richard, Ross, Paul, Alex, 
Brendan,



Agenda:



* Opens collection - 5 min (Stephen)

* Yocto Project status - 5 min (Stephen/team)

https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.8_Status

https://wiki.yoctoproject.org/wiki/Yocto_1.8_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_1.8_Features

YP 1.8 M4 rc1 build should be ready to go into QA by tomorrow.

YP 1.6.3 rc2 is coming out of QA soon.  But, its release might be delayed due 
to a recent SSL CVE.  Saul and others will review and decide if it need to be 
held and rebuild and rerun through QA.   Might delay this until early May.

YP 1.7.2 is planned for May.   If 1.6.3 is delayed it might push 1.7.2 until 
mid/late May.

* SWAT team rotation: Saul -> Paul/Ross

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

* Opens - 10 min

* Team Sharing - 10 min


Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:          (503) 712-0534
*    Cell:                                (208) 244-4460
* Email:                             stephen.k.jol...@intel.com

-- 
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to