Benoit Tellier created JAMES-4042:
-------------------------------------
Summary: Task manager: issues with long tasks
Key: JAMES-4042
URL: https://issues.apache.org/jira/browse/JAMES-4042
Project: James Server
Issue Type: Improvement
Components: rabbitmq, task
Affects Versions: master, 3.8.2
Reporter: Benoit Tellier
See JAMES-3955
Today a tasks per default obey a 1 day consumer timeout (configurable!)
Yet, we might have some tasks like deduplication that might take longer than a
day to complete...
As of today tihis means such a task would complete but very likely crash the
consumer.
Likely, getting such long jobs in the first place might not be the best idea.
Things like deduplication could be packaged in separate binaries that one could
run independently of James thus avoiding the issue altogether... We could allow
this as an alternative way to run such long tasks.
Moreover, I think if needed we could write a Proof Of Concept of running the GC
on top of something like Apache Spark to leverage parallele computations.
--