Reported here: https://dev.plone.org/plone/ticket/8939 — includes description/patch.

On Wed, 11 Feb 2009 06:40:06 -0800, Vinicio Balducci <[email protected]> wrote:


Further to my previous email, this afternoon, I have noticed that the
problem occurs when the "Start Date" and the "End Date" are selected in
the same day. The error does not occur if the two dates ("Start" and
"End") are selected in different days. The situation does not change
(i.e., the error persist) changing the site language, that affects the
way date/time is shown.This seems to be a bug, that was not present in
the previous release of Plone (e.g., 3.1.7). What has changed between
these two releaes?

Vinicio




--
Alexander Limi · http://limi.net


_______________________________________________
Setup mailing list
[email protected]
http://lists.plone.org/mailman/listinfo/setup

Reply via email to