Thanks for the information. It was very useful
josh
On Dec 14, 2007 4:18 PM, Christopher Browne <[EMAIL PROTECTED]>
wrote:
> "Josh Harrison" <[EMAIL PROTECTED]> writes:
> > I have a question regarding slony's switchover and failover option
> > The document says
> > "At the time of this writing switchover to another server requires the
> application to reconnect to the database. So in order to avoid any
> complications, we simply
> > shut down the web server. Users who use pg_pool for the applications
> database connections merely have to shut down the pool."
>
> If I describe this issue differently (and maybe that means changing
> the docs!), maybe it'll make it clearer...
>
> Any time you do switchover from one server to another, say, from "DB1"
> to "DB2", this requires that the applications that were connecting to
> DB1 drop those connections, and connect to DB2, instead.
>
> How you will accomplish this is hugely dependent on how you set your
> environment up.
>
> Options might include:
>
> - Stop the application, change "DB1" to "DB2" in a config file, and
> restart the application.
>
> - Use a DNS CNAME so that your application points to "DBSERVER;" that
> way, you initially have DNS set up so that DBSERVER is a CNAME
> pointing at DB1, and you later change it to be a CNAME pointing at
> DB2.
>
> You may need for your application to be restarted in order for it
> to know to reopen DB connections.
>
> - If you're using pg_pool, or something similar, then the
> reconfiguration involves reconfiguring pg_pool, rather than your DNS
> server.
>
> But for the most part, the behaviour is logically similar to the
> DNS-based example above.
>
> > 1 So does this mean that during the switchover, the web server
> > should be shut down and users will not be able to access the
> > database at that time?
>
> Ideally, yes. Cutting off access pretty forcibly tends to be a good
> idea during a switchover; that way, there aren't any lingering locks
> kicking around possibly preventing the switchover from completing
> quickly.
>
> > 2. Is there any time frame for this switchover ie., how long it
> > takes ? what does this depend on?
>
> The reason for it to take > 1s is that there are processes connected
> to either the former master node or the soon-to-be-master node,
> holding locks on tables that the switchover process needs to modify.
>
> > 3. Is there any other way to keep the web server up running during
> > this switch over operation?
>
> If you're using some mechanism like CNAME/pg_pool so that it's always
> pointing at "something current," and the application knows enough to
> re-open connections any time it finds they fail, that may "play OK."
> --
> output = ("cbbrowne" "@" "linuxfinances.info")
> http://cbbrowne.com/info/wp.html
> Your latest program has been judged UNTASTEFUL by the T daemon;
> and automatically deleted.
>
_______________________________________________
Slony1-general mailing list
[email protected]
http://lists.slony.info/mailman/listinfo/slony1-general