You could, if you want something slower and less scalable...
Quoting Dennis Mungai <[email protected]>:
Hello there,
You may want to look into a scheduling system such as Maui or Moab.
On Jan 5, 2016 2:14 AM, "GOLPAYEGANI, NAVID (GSFC-6190)"
<[email protected]> wrote:
Hi,
SLURM newbie here. Anybody have suggestions on how to do the scheduling
for a SLURM cluster for web submissions? We take orders from a webpage and
submit them as a single account to SLURM. We want to avoid having a
condition where web user2 single job has to wait behind web user1's
hundreds jobs. What kind of scheduling method and/or job submission method
would you guys recommend to use so that ideally a single web user can use
as many available nodes as possible when nobody else is using them but
can't (significantly) delay another web user's job.
Thank you,
Navid
______________________________________________________________________
This e-mail contains information which is confidential. It is
intended only for the use of the named recipient. If you have
received this e-mail in error, please let us know by replying to the
sender, and immediately delete it from your system. Please note,
that in these circumstances, the use, disclosure, distribution or
copying of this information is strictly prohibited. KEMRI-Wellcome
Trust Programme cannot accept any responsibility for the accuracy
or completeness of this message as it has been transmitted over a
public network. Although the Programme has taken reasonable
precautions to ensure no viruses are present in emails, it cannot
accept responsibility for any loss or damage arising from the use of
the email or attachments. Any views expressed in this message are
those of the individual sender, except where the sender specifically
states them to be the views of KEMRI-Wellcome Trust Programme.
______________________________________________________________________