Failing Unity state-owned power station gets private management

ArticleComments (3)
EmailPrintSave

By Bonifacio Taban Kuich

October 29, 2012 (BENTIU) – A private company has taken over the
management of a state-owned power station in Bentiu, Unity state, due
its inability to provide fuel in the wake of the national oil
production stoppage in January.


Map of South Sudan’s Unity State.
Chuol Bangoang Poon & Son Electricity Company Ltd. has taken charge of
the power station form Benitu Electricity Cooperation (BECO) which has
been unable to source sufficient fuel supplies since February.

Despite the shortage of fuel and the implementation of austerity
measures the company has taken on the task of returning electricity to
the area.

With the signing of agreements between Juba and Khartoum in September
there is hope that the resumption oil production will improve the
economic situations of both countries will improve.

Juba halted oil-production in a row with its northern neighbour over
the use of its infrastructure to pipe it out of landlocked South
Sudan. As oil accounts for more than 75 percent of South Sudan’s
revenues its stoppage had a dramatic effect on its economy.

Authorities from the state Ministry of Physical Infrastructure signed
a temporary deal with new company to run the power station, which
resumed operations on 15 October.

The company’s manager, Banasio Bangoang Yang says their aims are to
provide better services within both Bentiu and Rubkotna county.

“Our objectives in running this power station are to make sure that
the indigenous community of Bentiu town are benefiting from the
electricity. Our target is to make sure that every home has power
[...] we will switch on the power from 8.00am to 3:30 pm and from
7:00pm to midnight,” said Yang.


Unity State Flag (GoSS)
The Unity state fuel supply was partially cut off from Juba due to
recent flooding along the Mayiandit-Rumbek road. However, some local
traders have been bringing fuel via boat.

Power for Unity’s citizens was previously available for a 30SSDG per
month. The new company will charge 150SSDG per month and 20SSDG per
day for shops in the market; a move welcomed by local traders.

However, Obac Apaljam Doayowk Akol, a trader within Bentiu Suok Saba
(market seven), claims the services offered by the new company do not
match their schedules but acknowledged that current fuel prices are
causing them difficulties.

According to Peter Chany Gatjiek, director of electricity in the
Ministry of Physical Infrastructure, “we don’t have enough fuel to
operate this power station.”

He explained that the power station has three engines, running running
on 2500 Kilo Volt Amperes (KVA), 810KVA and 2.5 Megawatts. Operating
for 10 hours per day requires 11 barrels of oil, “so it is too much.
In the town there is no fuel.”

Gatjiek said that if the new company “gets the fuel on the black
market it is up to him”. He added that the agreement with the company
is a temporary arrangement and when the oil transit deal between Juba
and Khartoum takes effect, the government will resume responsibility.

Juba ordered oil companies to restart oil production in October.
According to the national minister for petroleum it will take three
months for it to reach international markets.

For eight months many of those who previously had electricity in Unity
state have been without it or have been relying on generators fuelled
by costly oil from the local market.

(ST)

-- 
You received this message because you are subscribed to the Google Groups 
"South Sudan Info - The Kob" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit https://groups.google.com/groups/opt_out.


Reply via email to