Brian , I was told many years ago that this little arrangement was there to assure that all the water had been removed from the required 4 ft. of pipe on the heated side of the test connection before the wall penetration.This would be removed after testing and tied to the ITC for re-use by the next inspector. I don't know if this is what everyone else has as an opinion , but that's my story and I'm stikin' to it.
---- Brian Harris <[email protected]> wrote: > > Quick question, > What is the reason for having a piece of removable pipe on a Dry Pipe system > test connection as shown in Fig. A.8.17.4.3 (2007) > > Thanks! > Brian > > _______________________________________________ > Sprinklerforum mailing list > [email protected] > http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum > > For Technical Assistance, send an email to: [email protected] > > To Unsubscribe, send an email to:[email protected] > (Put the word unsubscribe in the subject field) _______________________________________________ Sprinklerforum mailing list [email protected] http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum For Technical Assistance, send an email to: [email protected] To Unsubscribe, send an email to:[email protected] (Put the word unsubscribe in the subject field)