Having an onsite meeting tomorrow. If it's as bad as the pictures I've seen I'm 
not moving a damn thing until he signs off on it.

Brian Harris, CET
BVS Systems Inc.
bvssytemsinc.com


-----Original Message-----
From: Sprinklerforum [mailto:[email protected]] On 
Behalf Of Travis Mack, SET
Sent: Wednesday, April 13, 2016 1:53 PM
To: [email protected]
Subject: Re: Insulation R Values

That is a totally different animal then.  If the builder changes the 
parameters, then he pays.  At least in a perfect world it would be, but we know 
that won't happen.

Travis Mack, SET
MFP Design, LLC
2508 E Lodgepole Drive
Gilbert, AZ 85298
480-505-9271
fax: 866-430-6107
email:[email protected]

http://www.mfpdesign.com
https://www.facebook.com/pages/MFP-Design-LLC/92218417692
Send large files to us via: https://www.hightail.com/u/MFPDesign
LinkedIn: https://www.linkedin.com/in/travismack

On 4/13/2016 10:50 AM, Brian Harris wrote:
> building inspector said he wanted more insulation so the GC just piled it on 
> so they could pass inspection, never thinking about the effects on the 
> sprinkler system deflector distances.

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to