I'm not sure if its pre-made but the best I can gather is it's a room to
pull data cabling into the building.

 

Jerry Van Kolken

Millennium Fire Protection

(760) 722-2722

 

From: Sprinklerforum [mailto:[email protected]]
On Behalf Of Matthew J Willis
Sent: Wednesday, August 29, 2018 6:27 AM
To: [email protected]
Subject: RE: When is it a Floor?

 

IBC Chapter 2 calls a basement a story, and a story as the space between
floors. Also the distance between finished floors.

 

Vault is defined elsewhere as an underground chamber basically.

Seems clear-cut until we are asked to prove.

 

What is a "Splice Vault" anyway?

Is the vault pre-made then lowered into position? Like our valve vaults?

 

 

R/

Matt

 

Matthew J. Willis, CWBSP

Design Manager /3-D Specialist

 <http://rapidfireinc.com/> Rapid Fire Protection Inc.

1530 Samco Road

Rapid City, SD 57702

Office-605.348.2342

Direct Line-605.593.5063

Cell-605.391.2733

Fax:-605.348.0108

 

cid:[email protected]

 

From: Sprinklerforum <[email protected]> On
Behalf Of Jerry Van Kolken
Sent: Tuesday, August 28, 2018 5:28 PM
To: [email protected]
Subject: When is it a Floor?

 

I have a 2 story building with a 600sqft "Splice Vault" underneath it. The
reviewer is calling this out as basement, hence 3 stories, which would
require floor controls. In 13-8.2.4 (2016) it discuss floor controls not
being required in apartment situations, and floor areas above, but nothing
for below. Is there any references I could look at to not have to install
extra floor controls?

 

Jerry Van Kolken

Millennium Fire Protection Corp.

2950 San Luis Rey Rd.

Oceanside, CA 92058

(760) 722-2722 FX 722-2730

 

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to