I'm having pipe supported with on pipe clamp with rod from each ear into 
concrete insert at the ground. The piping is sitting at about 6" above the 
floor. Both parts of the pipe clamp are intended to be used wrapping the pipe 
at each support location. I'm are being asked to provided seismic bracing for 
this piping or reason for the omission of the bracing. Since this area has a CP 
valve over 0.5 I can't find any exceptions that would allow  for this 
requirement to  omitted.

IS there something I'm missing?

Jerry Van Kolken
Millennium Fire Protection Corp.
2950 San Luis Rey Rd.
Oceanside, CA 92058
(760) 722-2722 FX 722-2730

CONFIDENTIALITY NOTICE This e-mail and any attachments are for the sole use of 
the intended recipients and contain information that may be confidential or 
legally privileged. If you have received this e-mail in error, please notify 
the sender by reply e-mail and delete the message. Any disclosure, copying, 
distribution, or use of this communication by someone other than the intended 
recipient is prohibited.
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to