Seems were seeing more and more wood framed buildings these days and with that comes attics. Just curious what the general school of thought is with running piping in these spaces. Is it better to run the Main high under the ridges with back to back heads (size permitting) or is it better run Mains low and then run smaller Mains up the slope feeding branches at the ridges? I'm working on a job now that kinda resembles a long rectangle with no center (courtyards). I have all the heads laid out with B/B at the ridges, some AP's in the corners & throughout as needed. Just looking for ideas from some of you with much more attic experience than I have.
Brian Harris, CET BVS Systems Inc. Design Manager bvssystemsinc.com<http://bvssystemsinc.com/> Phone: 704.896.9989 Fax: 704.896.1935 _______________________________________________ Sprinklerforum mailing list [email protected] http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org