Thanks

I was using the categories column.

Regards

Martyn 

--- In [email protected], Jérôme Laheurte <fra...@...> wrote:
>
> 
> Le 5 janv. 2010 à 12:34, martynbedford a écrit :
> 
> > I have just installed the latest version of Taskcoach and have a question 
> > about how you should handle the categories for sub tasks.
> > 
> > When I create a task whilst I have a category selected the task get created 
> > assigned to that category, but when I create a sub task there are no 
> > categories selected, it would be great if it defaulted to the category of 
> > the parent task so I can automatically create sub tasks without having to 
> > go and find the appropriate category.
> > 
> > Is this possible?
> 
> Actually, subtasks implicitely belong to their parent's categories already. 
> Right-click on the tree column headers and check the "Overall categories" 
> item to show a column in that task viewer with all, actual and inherited, 
> categories.
> 
> Cheers
> Jérôme
>


Reply via email to