I have posted the same in StackOverflow
<https://stackoverflow.com/questions/61099510/decomission-yarn-resource-manager-node>
and
did not get much reply there also. Anyone any thoughts on this?

On Wed, Apr 8, 2020 at 4:51 PM Debraj Manna <subharaj.ma...@gmail.com>
wrote:

> Hi
>
> I have 3 nodes running only resource-manager. I want to change it to 2
> nodes. Can someone let me know what is the recommended a way to
> decommission a node running resource-manager? I have seen the below link
> but it explains only about nodemanager
>
>
> https://hadoop.apache.org/docs/current/hadoop-yarn/hadoop-yarn-site/GracefulDecommission.html
>
> Can I just do the following (downtime is not a problem here)
>
>    1. Stop resourcemanager and nodemanager in all the nodes
>    2. Remove the node details from all the yarn-site.xml files
>    3. Restart the resourcemanager and nodemanager services in the
>    remaining nodes
>
> Hadoop Version - 2.6.0
>